Chemical Room Construction

Duffy Contractors were appointed to provide new Chemical Rooms at a large confidential facility. The area had previously been used as a warehouse space which required extensive works to the concrete floor and slab to form chemical trenches.

Scope of Works:

  • Concrete floor cutting and coring
  • Civils excavations and rubble removal
  • Electrical plant used in indoor area
  • Shuttering and pouring new concrete trenches
  • Installation of steel grating to trenches
  • Chemical Resistant Coatings applied to floors
  • Small office area provided
  • Supply and install of signage, fixtures, fittings and painting
  • Zero impact to factory production

Project Details:

Client: Confidential

Design Team: Confidential

Value: €2,000,000

Time frame: 6 months